Southwestern Vermont Medical Center

Cx Associates conducted a retrocommissioning qualification study for the chilled water plant at the Southwestern Vermont Medical Center. Our review of the facility focused on its chilled water plant, the BAS, as well as pumps and the cooling tower. Our study resulted in four measures we recommended to the owner. These four measures resulted in estimated annual savings of $17,000, which would result in a payback period of just 1.4 years.

General Project Information:

  • Size: 241,000 SF
  • Qualification Phase Budget: $7,625